2022 Mill and Overlay Project

About2022 Mill and Overlay

The 2022 Mill and Overlay Improvements Project will take place starting early June in the Thompson Grove neighborhood. This project consists of the removal and replacement of the top two inches of pavement. The project will also include spot curb and pedestrian ramp removal and replacement, along with minor utility adjustments. 

The details

  • You can learn more about the project and see a map of the area in this brochure.
  • Construction is anticipated to occur between early June and late August 2022. Street construction is weather dependent, which means the schedule is subject to change. 
  • There are approximately 6.5 miles of residential streets within this project.
  • The upper 2 inches of pavement will be removed and 2 inches of new pavement will be placed. Concrete pedestrian ramps and adjacent curb and gutter will be removed and replaced to meet ADA compliance.
  • Safety is the highest priority of everyone involved in this project. While the contractor will do their best to provide warning signs, barricades, and observation within the project areas, we do ask that you remind children to stay clear of the construction site and equipment.

Contact

Graduate Engineer Jared Juth
jjuth@cottagegrovemn.gov
Call 651-458-2829 to leave a message to receive follow-up calls