Project Summary
Well #13 will be constructed to replace two existing wells that are contaminated with PFAS. The new well will be located on the same site as the new Low Zone Water Treatment Plant, in the southwest area of the city, in the northeast corner of the intersection of Ideal Avenue South and 110th Street South. The well is scheduled to be fully operational with the commissioning of the Low Zone Water Treatment Plant. This new well is being funded by the 3M Settlement Agreement.
Status
A preliminary test well has been drilled and it has been confirmed that the proposed site for the new well is suitable. Design for the new well is scheduled to begin this spring with construction starting in the fall. The well is scheduled to be fully operational with the commissioning of the Low Zone Water Treatment Plant.